1.

A can finish a work in 18 days and B can do the same work in 5 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?

A. 6 days
B. <table><tr><td rowspan="2">5</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>1</center></td><td rowspan="2">days</td></tr><tr><td style="text-align: center;">2</td></tr></table>
C. 5 days
D. 8 days
Answer» B. <table><tr><td rowspan="2">5</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>1</center></td><td rowspan="2">days</td></tr><tr><td style="text-align: center;">2</td></tr></table>