A can do one and a half as much of a work which B can do in one day. B alone can do a piece of work in 18 days. They together can finish that work in |
| A. | <table><tr><td rowspan="2">10</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>1</center></td><td rowspan="2">days </td></tr><td align="center">5</td></table> |
| B. | |
| C. | <table><tr><td rowspan="2">11</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>1</center></td><td rowspan="2">days </td></tr><td align="center">5</td></table> |
| D. | <table><tr><td rowspan="2">5</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>1</center></td><td rowspan="2">days </td></tr><td align="center">5</td></table> |
| E. | <table><tr><td rowspan="2">7</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>1</center></td><td rowspan="2">days </td></tr><td align="center">5</td></table> |
| Answer» E. <table><tr><td rowspan="2">7</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>1</center></td><td rowspan="2">days </td></tr><td align="center">5</td></table> | |