1. |
A can do a work in 60 days and B can do the same work in 40 days. They work together for 12 days and then A goes away. In how many days will B finish the remaining work? |
A. | 16 days |
B. | 20 days |
C. | 25 days |
D. | 28 days |
Answer» C. 25 days | |