| 1. |
A can do a work in 12 days and B can do it in 16 days. A and B started the work jointly and A left 2 days before the work is finished. Find the number of days they took to finish the work.(1) (2) |
| A. | 6 days |
| B. | 7 days |
| C. | 9 days |
| D. | 8 days |
| Answer» E. | |