A can do a piece of work in 20 days and B in 30 days. They work together for 7 days and then both leave the work. Then C alone finishes the remaining work in 10 days. In how many days will C finish the full work? |
A. | 25 days |
B. | 30 days |
C. | 24 days |
D. | 20 days |
Answer» D. 20 days | |