A can do a piece of work in 20 days and B in 30 days. They work together for 7 days and then both leave the work. Then C alone finishes the remaining work in 10 days. In how many days will C finish the full work?

A. 25 days
B. 30 days
C. 24 days
D. 20 days
Answer» D. 20 days