1.

A can complete 2/3 of a work in 4 days and B can complete 3/5 of the work in 6 days. In how many days can both A and B together complete the work ?

A. 3
B. 2
C.
D. <table><tr><td rowspan="2">3</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>3</center></td><td rowspan="2"></td></tr><td align="center">4</td></table>
E. <table><tr><td rowspan="2">2</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>7</center></td><td rowspan="2"></td></tr><td align="center">8</td></table>
Answer» D. <table><tr><td rowspan="2">3</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>3</center></td><td rowspan="2"></td></tr><td align="center">4</td></table>


Discussion

No Comment Found