1.

A borrow pit soil has a dry density of 17 kN/m 3 . How many cubic meters of this soil will be required to construct an embankment of 100 m 3 volume with a dry density of 16 kN/m 3 .

A. 94 m 3
B. 106 m 3
C. 100 m 3
D. 90 m 3
Answer» B. 106 m 3


Discussion

No Comment Found

Related MCQs