A, B, C completes 37.5%, 44.44%, 66.66% of a work in 9 days, 8 days, 8 days respectively. Then find how many days they take to complete 65% of work together? |
A. | 3.6 days |
B. | 4.4 days |
C. | 4.9 days |
D. | 1.2 days |
Answer» B. 4.4 days | |