A, B , C can finish a work in 10, 12, and 15 days respectively. They start working together. If B stops after 2 days, how long would it take A and C to finish the remaining work

A. 3 days
B. $$ {3{8 over 11}} days$$
C. $$ {2{6 over 11}} days$$
D. $$ {3{6 over 11}} days$$
Answer» B. $$ {3{8 over 11}} days$$