A, B and C can do a piece of work in 16, 32 and 48 days, respectively. They all begin together. A work continuously till it is finished, C leaves the work 2 days before its completion and B leaves the work in 1 days before its complete. In what time is the work finished ? |
| A. | 10 days |
| B. | 20 days |
| C. | 15 days |
| D. | 30 days |
| E. | None of these |
| Answer» F. | |