1.

A and B working separately can do a piece of work in 9 and 12 days respectively. If they work for a day alternately with A beginning, the work would be completed in

A. 10 2/3 days
B. 10 1/2 days
C. 10 1/4 days
D. 10 1/3 days
Answer» D. 10 1/3 days