A and B together can do a work in 12 days. B and C together do it in 15 days. If A s efficiency is twice that of C, then the days required for B alone to finish the work is |
| A. | 60 days |
| B. | 30 days |
| C. | 20 days |
| D. | 15 days |
| Answer» D. 15 days | |