A and B together can complete a work in 24 days. B alone does 1/3 rd part of this work in 12 days. How many days will A alone take to complete the remaining work? |
| A. | 24 days |
| B. | 36 days |
| C. | 48 days |
| D. | 72 days |
| Answer» D. 72 days | |