| 1. |
A and B together can complete a work in 15 days. A is 50% more efficient worker than B. How long will A take to complete the work alone ? |
| A. | 20 days |
| B. | 21 days |
| C. | 21.4 days |
| D. | 22.5 days |
| E. | None of these |
| Answer» F. | |