| 1. |
A and B together can complete a piece of work in 12 days, B and C can do it in 20 days and C and A can do it in 15 days. A, B and C together can complete it in |
| A. | 12 days |
| B. | 6 days |
| C. | 8 days |
| D. | 10 days |
| Answer» E. | |