A and B together can complete a job in 8 days. Both B and C, working alone can finish the same job in 12 days, A and B commence work on the job, and work for 4 days, where upon A leaves , B continues for 2 more days , and then he leaves too, C now starts working, and finishes the job. How many days will C require to finish the remaining work? |
A. | 5 days |
B. | 8 days |
C. | 3 days |
D. | 4 days |
Answer» E. | |