A and B can do a job in 6 and 12 days respectively. They began the work together but A leaves after 3 days. Then the total number of days needed for the completion of the work is : |
| A. | 4 days |
| B. | 5 days |
| C. | 6 days |
| D. | 9 days |
| Answer» D. 9 days | |