1.

A and B can complete a piece of work in 80 days and 120 days respectively. They started working together but A left after 20 days. After another 12 days C joined B and they completed the work in 28 more days. In how many days can C alone complete the work?

A. 110 days
B. 112 days
C. 114 days
D. 120 days
Answer» C. 114 days