1. |
A alone can complete a work in 6 days and B can complete this work alone in 8 days. They can complete this work in 3 days with the help of C. If they are paid Rs. 6400 for this work, then find the share of C. |
A. | 400 |
B. | 800 |
C. | 1600 |
D. | 3200 |
Answer» C. 1600 | |