A alone can complete a work in 18 days and B alone in 15 days. B alone worked at it for 10 days and then left the work. In how many more days, will A alone complete the remaining work ? |
| A. | 5 days |
| B. | |
| C. | <table><tr><td rowspan="2">5</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>1</center></td><td rowspan="2">days</td></tr><tr><td style="text-align: center;">2</td></tr></table> |
| D. | 6 days |
| E. | 8 days |
| Answer» D. 6 days | |