90 persons can complete a job in 32 days. 12 days after they started working, 60 more persons joinedthem. How many days will they now take to complete the remaining work? |
| A. | 10 |
| B. | 12 |
| C. | 14 |
| D. | 16 |
| Answer» C. 14 | |