| 1. |
9 excavators working 10 hrs. a day remove 2500 cubic feet of earth in 3 days. How many excavators working 6 hrs. a day are required to remove 5000 cube feet of earth in 2 days? |
| A. | 55 |
| B. | 50 |
| C. | 45 |
| D. | 40 |
| Answer» D. 40 | |