1. |
8 men and 4 women together can complete a piece of work in 6 days. Work done by a man in one day is double the work done by a woman in one day. If 8 men and 4 women started working and after 2 days, 4 men left and 4 new women joined, in how many more days will the work be completed? |
A. | 5 days |
B. | 8 days |
C. | 6 days |
D. | 4 days |
E. | 9 days |
Answer» B. 8 days | |