| 1. |
40 men can complete a work in 18 days. Eight days after they started working together, 10 more men joined them. How many days will they now take to complete the remaining work ? |
| A. | 6 |
| B. | 8 |
| C. | 10 |
| D. | 12 |
| Answer» C. 10 | |