12 men can complete a work in 90 days. 30 days after they started work, 2 men left and 8 men joined. How many days will it take to complete the remaining work ? |
| A. | 90 days |
| B. | 60 days |
| C. | 40 days |
| D. | 50 days |
| Answer» D. 50 days | |