10. A and B can do a piece of work in 10 days, B and C in 12 days and C and A in 15 days. If B alone works for 15 days and then joined by A and C, in how many days will the work be finished? |
| A. | 20 days |
| B. | 15 days |
| C. | 16 days |
| D. | 18 days |
| Answer» E. | |