Sudhir and Shyam can do a work in 12 days, while Shyam alone can complete it in 30 days. In how many days can Sudhir complete that work alone? |
A. | 20 days |
B. | 18 days |
C. | 28 days |
D. | 30 days |
Answer» B. 18 days | |