| 1. | What is the full form of Mcfd? | 
| A. | Millions of standard cubic feet per day | 
| B. | Thousands of standard cubic feet per day | 
| C. | Hundreds of standard cubic feet per day | 
| D. | Standard cubic feet per day | 
| Answer» C. Hundreds of standard cubic feet per day | |
| 2. | Inflow after flow deliverability curve, which of the plot we generally use? | 
| A. | P<sub>wf</sub> vs t | 
| B. | P<sub>i</sub> vs t | 
| C. | (P<sub>i</sub><sup>2</sup> P<sub>wf</sub><sup>2</sup>) vs q | 
| D. | (P<sub>i</sub><sup>2</sup> P<sub>wf</sub><sup>2</sup>) vs t | 
| Answer» D. (P<sub>i</sub><sup>2</sup> P<sub>wf</sub><sup>2</sup>) vs t | |
| 3. | If a well is producing above bubble point pressure then the Productivity Index will be constant for a wide range of drawdowns. | 
| A. | True | 
| B. | False | 
| Answer» B. False | |
| 4. | Specific Productivity index is _____ | 
| A. | q/(P<sub>i</sub>-P<sub>wf</sub>) | 
| B. | Productivity Index/Fluid density | 
| C. | (P<sub>i</sub>-P<sub>wf</sub>)/q | 
| D. | Productivity Index/Length of the producing zone | 
| Answer» E. | |
| 5. | What is Absolute Open Flow Potential? | 
| A. | The production rate if the bottom hole flowing pressure can be reduced to zero | 
| B. | The production rate if the bottom hole shut-in pressure can be reduced to zero | 
| C. | The production rate if the bottom hole flowing pressure can be reduced to 1 atm | 
| D. | The production rate if the bottom hole shut-in pressure can be reduced to 1 atm | 
| Answer» B. The production rate if the bottom hole shut-in pressure can be reduced to zero | |
| 6. | What is the formula of the Productivity Index? | 
| A. | q/(P<sub>i</sub>-P<sub>wf</sub>) | 
| B. | (P<sub>i</sub>-P<sub>wf</sub>)/q | 
| C. | V/(P<sub>i</sub>-P<sub>wf</sub>) | 
| D. | q/(P<sub>i</sub>.P<sub>wf</sub>) | 
| Answer» B. (P<sub>i</sub>-P<sub>wf</sub>)/q | |
| 7. | Productivity or Deliverability Tests can be applied to Non- Darcy, below the bubble point flow conditions. | 
| A. | True | 
| B. | False | 
| Answer» B. False | |