MCQOPTIONS
Saved Bookmarks
This section includes 7 Mcqs, each offering curated multiple-choice questions to sharpen your Geotechnical Engineering knowledge and support exam preparation. Choose a topic below to get started.
1. |
The method that is used to avoid the further increase in tilt is ___________ |
A. | Pushing by jack |
B. | Eccentric loading |
C. | Strutting the well |
D. | Pushing the well |
Answer» D. Pushing the well | |
2. |
In which of the following methods, hydraulic jack is used to counter attack the tilt in the well? |
A. | Pulling the well |
B. | Eccentric loading |
C. | Pushing by jack |
D. | Pulling the well |
Answer» D. Pulling the well | |
3. |
The radius of the well curb should be kept _________ larger than the outside radius of well steining. |
A. | 2 cm and 4 cm |
B. | 2 m |
C. | All of the mentioned |
D. | None of the mentioned |
Answer» B. 2 m | |
4. |
Unequal dredging of well causes _________ |
A. | Collapsing of well |
B. | Tilting |
C. | Open excavation |
D. | Maximum skin friction |
Answer» C. Open excavation | |
5. |
Excavation of soil inside the well in river beds can be done by ________ |
A. | Auger |
B. | Sending in Workers |
C. | Special equipment |
D. | None of the mentioned |
Answer» B. Sending in Workers | |
6. |
The inside shuttering of the well curb is made up of _________ |
A. | Steel |
B. | Wood |
C. | Brick masonry |
D. | Concrete |
Answer» D. Concrete | |
7. |
Laying of the well curb in river bed having water, is done by _________ |
A. | Draining out the water |
B. | Diverting the water |
C. | Constructing cofferdams |
D. | None of the mentioned |
Answer» D. None of the mentioned | |