| 1. |
Short circuit method is used for _____________ |
| A. | drying out the transformer and oil simultaneously in the transformer tank |
| B. | drying the transformer only, out of its tank. |
| C. | for any type of drying |
| D. | never used |
| Answer» D. never used | |
| 2. |
Which readings should be taken while drying out process of transformer? |
| A. | Insulation reading between HV and LV |
| B. | Temperature |
| C. | Time |
| D. | Insulation, temperature, time all readings |
| Answer» E. | |
| 3. |
For 400 kV transformer, moisture content required is _______________ |
| A. | below 0.1% |
| B. | below 0.5% |
| C. | above 0.5% |
| D. | below 1% |
| Answer» C. above 0.5% | |