| 151. |
Set of programs which consist of full set of documentations is termed as |
| A. | database packages |
| B. | file packages |
| C. | bus packages |
| D. | software packages |
| Answer» E. | |
| 152. |
Last step in process of problem solving is to |
| A. | design a solution |
| B. | define a problem |
| C. | practicing the solution |
| D. | organizing the data |
| Answer» D. organizing the data | |
| 153. |
Which one is NOT a project management activity? |
| A. | identify tasks |
| B. | estimate task duration |
| C. | assign resources |
| D. | assess risks |
| Answer» E. | |
| 154. |
Which of the following is a graphical network model that depicts a project’s tasks and the relationships between those tasks? |
| A. | PERT chart |
| B. | WBS |
| C. | Gantt chart |
| D. | Line chart |
| Answer» B. WBS | |
| 155. |
Which of the project management charts is most effective when you want to study the relationships between tasks? |
| A. | Gantt chart |
| B. | PMBOK chart |
| C. | WBS chart |
| D. | PERT chart |
| Answer» E. | |
| 156. |
All of the following are the guidelines for selecting and recruiting team members, except |
| A. | select the best task for each person |
| B. | promote harmony by selecting team members who will complement and work well with each other |
| C. | plan for the future |
| D. | recruit team members with extensive systems development experience |
| Answer» E. | |
| 157. |
An inter-task dependency in which two tasks must finish at the same time is referred to as |
| A. | Start-to-finish (SF) |
| B. | Finish-to-finish (FF) |
| C. | Finish-to-start (FS) |
| D. | Start-to-start (SS) |
| Answer» C. Finish-to-start (FS) | |
| 158. |
Which of the following is the estimated amount of time required to complete a task, based on a weighted average of pessimistic, optimistic, and expected duration? |
| A. | minimal duration |
| B. | earliest completion |
| C. | weighted average duration |
| D. | most likely duration |
| Answer» E. | |
| 159. |
From a project management perspective, a project is considered a success if |
| A. | the system is delivered on time |
| B. | the system is developed within budget |
| C. | the system is acceptable to the customer |
| D. | all of the above |
| Answer» E. | |
| 160. |
A task of developing a technical blueprint and specifications for a solution that fulfills the business requirements is undertaken in the following phase of the system development process |
| A. | system initiation |
| B. | system implementation |
| C. | system analysis |
| D. | system design |
| Answer» E. | |
| 161. |
Process management is |
| A. | the ongoing activity of recording facts and specifications for a system for current and future reference |
| B. | the activity of scoping, planning and staffing the development of a system |
| C. | the activity of organizing the development of a system |
| D. | the activity of documenting, managing, and continually improving the process of systems development |
| Answer» E. | |
| 162. |
All of the following are the project management causes of failed projects, except |
| A. | lack of organization’s commitment to the system development methodology |
| B. | lack of project documentation |
| C. | premature commitment to a fixed budget and schedule |
| D. | failure to adopt to business change |
| Answer» C. premature commitment to a fixed budget and schedule | |