Explore topic-wise MCQs in Petroleum Production Operations.

This section includes 5 Mcqs, each offering curated multiple-choice questions to sharpen your Petroleum Production Operations knowledge and support exam preparation. Choose a topic below to get started.

1.

What is wait on cement?

A. The time required for cementing
B. The time required for casing placement
C. The time required for the cement to solidify
D. The time required for the cement to just place around the casing
Answer» C. The time required for the cement to solidify
2.

The Cement Retainer is a drillable packer.

A. True
B. False
Answer» B. False
3.

Why does coiled tubing have a faster rate of penetration than rotary drilling rig?

A. It doesn t need a special crew
B. Since connection needs to be made
C. It is a continuous reel
D. It requires more joined pipes to connect with
Answer» D. It requires more joined pipes to connect with
4.

When is the retrievable squeeze packers used?

A. Resetting permits flexibility and to find casing leak
B. Low-pressure application
C. High-pressure application
D. At the time of Drilling
Answer» B. Low-pressure application
5.

Squeeze packers are used for low-pressure squeeze cementing.

A. True
B. False
Answer» C.