1. |
The safety of a hydraulic structure founded on a pervious foundation can be ensured by:i. Provision sufficient length of its concrete floor.ii. Providing sufficient depth of its concrete floor.iii. Provision a downstream cutoff of some reasonable depth. |
A. | i and ii |
B. | i and iii |
C. | i, ii and iii |
D. | ii and iii |
Answer» D. ii and iii | |
2. |
Backward erosion piping takes place when the phreatic line cuts the downstream face of the dam and seepage pressure is high. |
A. | True |
B. | False |
Answer» B. False | |
3. |
Heave piping may occur on the _______________ |
A. | downstream of sheet pile or cut off wall |
B. | upstream of sheet pile or cut off wall |
C. | body of earth structure |
D. | below the foundation |
Answer» B. upstream of sheet pile or cut off wall | |
4. |
The structure finally subsides in the hollow formed in the foundation in which failure? |
A. | Collapse |
B. | Overturning |
C. | Undermining |
D. | Uplift |
Answer» D. Uplift | |
5. |
The uplift pressure is not important for the upstream apron during considerations of failure due to uplift. |
A. | True |
B. | False |
Answer» B. False | |
6. |
What are the two main causes of failure of hydraulic structure on the pervious foundation? |
A. | Seepage and Over-turning |
B. | Undermining and Uplift |
C. | Over-turning and Piping |
D. | Overturning and Uplift |
Answer» C. Over-turning and Piping | |