			MCQOPTIONS
 Saved Bookmarks
				This section includes 10 Mcqs, each offering curated multiple-choice questions to sharpen your Railway Engineering knowledge and support exam preparation. Choose a topic below to get started.
| 1. | A railway line passes through a terrain which crosses watershed areas of two or more streams. Which type of alignment can be preferred? | 
| A. | Plane alignment | 
| B. | Mountain alignment | 
| C. | Cross country alignment | 
| D. | Valley alignment | 
| Answer» D. Valley alignment | |
| 2. | The alignment of railway line should be such that it attracts minimum traffic. | 
| A. | True | 
| B. | False | 
| Answer» C. | |
| 3. | What formula can be used to calculate the Maximum Annual Return of a rail alignment? (Given: R = Gross revenue earned by railway line; E = Annual running expenses). | 
| A. | R + E | 
| B. | R E | 
| C. | R / E | 
| D. | E / R | 
| Answer» C. R / E | |
| 4. | At what angle should a railway line cross a road? | 
| A. | 90 | 
| B. | 30 | 
| C. | 60 | 
| D. | 45 | 
| Answer» B. 30 | |
| 5. | The alignment of a rail line should pass through a place that faces ______ the direction of wind. | 
| A. | Towards | 
| B. | Away from | 
| C. | Towards or away from | 
| D. | At an angle of 30 degree from | 
| Answer» C. Towards or away from | |
| 6. | The spiral method, also known as ________ method is used in _______ | 
| A. | Complete loop; narrow valley | 
| B. | Incomplete loop; flat terrain | 
| C. | Complete loop; flat terrain | 
| D. | Incomplete loop; narrow valley | 
| Answer» B. Incomplete loop; flat terrain | |
| 7. | Which of the following method of rail alignment is preferred in case of steep side slopes? | 
| A. | Zigzag line method | 
| B. | Switch back method | 
| C. | Spiral method | 
| D. | Cubic method | 
| Answer» C. Spiral method | |
| 8. | If the gradient exceeds the ruling gradient, which technique much be adopted? | 
| A. | Control technique | 
| B. | Development technique | 
| C. | Management technique | 
| D. | Ruling technique | 
| Answer» C. Management technique | |
| 9. | Obligatory points are also known as ________ | 
| A. | Controlling points | 
| B. | Saddle points | 
| C. | Rolling points | 
| D. | Important points | 
| Answer» B. Saddle points | |
| 10. | In railways terminology, what do obligatory points mean? | 
| A. | Points through which the railway line must pass | 
| B. | Points through which the railway line should not pass | 
| C. | Points where railway signals must be placed | 
| D. | Points where rail crossings are provided | 
| Answer» B. Points through which the railway line should not pass | |