1.

PMI updated and approved the Code of Ethics for project managers in

A. 1995
B. 2006
C. 1988
D. both a and b
Answer» E.
2.

Formal analytic method such as SWOT analysis is used for the identification of

A. Mission
B. Vision
C. Strategies
D. All of the Above
Answer» E.
3.

Fisher have developed a negotiation technique that tends to maintain

A. 2 requirements
B. 3 requirements
C. 4 requirements
D. 5 requirements
Answer» C. 4 requirements
4.

Estimating the implications for project objectives, is done at the

A. Qualitative Risk Analysis
B. Risk Response
C. Risk Identification
D. Quantitative Risk Analysis
Answer» E.
5.

Commitment of resources to the project must be forthcoming from

A. Functional managers
B. Senior Management
C. both a and b
D. Project mangers
Answer» D. Project mangers
6.

No matter how ornate the procedure is, most firms actually have only priorities of

A. 1 level
B. 2 levels
C. 3 levels
D. 5 levels
Answer» D. 5 levels
7.

Resource Leveling is the approach to even out the peaks of

A. Resources
B. Quality
C. Performance
D. Lackage
Answer» B. Quality
8.

For some extent, risk management techniques can be applied to

A. Scope Change
B. Partnering
C. Chartering
D. Technological uncertainty
Answer» B. Partnering
9.

Multiple screens are employed to try to narrow down the number of competing projects in step

A. Resources availability
B. Data collection step
C. Reduce the criteria set
D. Prioritizing projects
Answer» D. Prioritizing projects
10.

Most conflicts have their roots in uncertainty, and negotiation is a way of managing the

A. Resultant Risk
B. Failure
C. Uncertainty
D. Inputs
Answer» B. Failure
11.

In reduction of criteria set, the first screen is each project's support of the

A. Timing
B. Cost
C. Quality
D. Goal
Answer» E.
12.

Discounted cash flow method determines the net present value of all cash flows by discounting them with the required

A. Hurdle rate
B. Cutoff rate
C. Rate of return
D. All of the Above
Answer» E.
13.

Project success is dependent on support from parent organization's

A. Senior management
B. Middle management
C. Project management
D. Lower management
Answer» B. Middle management
14.

PMIS stands for

A. Project Management Information System
B. Project Management Integrated System
C. Project Management Inline System
D. Project Management Input System
Answer» B. Project Management Integrated System
15.

A pure project organization overlaid on the functional divisions of the parent firm, is known as

A. Mixed Organizational System
B. Pure Project Organization
C. The Matrix Organization
D. Virtual Organization
Answer» D. Virtual Organization
16.

The PM needs credibility of kinds:

A. Two
B. Three
C. Four
D. Six
Answer» B. Three
17.

A combination of interrelated activities and events depicted with arcs and nodes, is known as

A. Listing
B. Nodes Sorting
C. Team Management
D. Network
Answer» E.
18.

Schedules are a major source of conflicts in the

A. Project formation
B. Project Buildup
C. Main program
D. Project Phase-out
Answer» D. Project Phase-out
19.

The responsibility of allocating and controlling resources and skills to the projects is of

A. Middle Management
B. Project council
C. Control Team
D. Project Profile Team
Answer» C. Control Team
20.

A frim can select the organizational structure that seems to offer the most

A. Efficient
B. Effective
C. both a and b
D. Low Capital investment
Answer» D. Low Capital investment
21.

The individual who has the responsibility for performing and completing a task sometimes overestimates

A. Time required
B. Cost required
C. both a and b
D. Quality required
Answer» D. Quality required
22.

The process of cutting a project's budget enough to stop progress without actually killing the project, is

A. Termination by Integration
B. Termination by starvation
C. Termination by murder
D. Termination by Addition
Answer» C. Termination by murder
23.

Most projects fail because of insufficient top management support, poor planning and

A. Wrong Project manager
B. Inappropriate use of project form
C. both a and b
D. None of the Above
Answer» D. None of the Above
24.

PM is responsible for the project, but the functional managers will probably make some of the fundamental and critical

A. Project Planning
B. Project manufacturing
C. Project Decisions
D. Project Execution
Answer» D. Project Execution
25.

What is used to categorize risks, assumptions, and environments so that all risk management groups can access work done on risk management?

A. List of Indexes
B. List of categories
C. List of keywords
D. both b and c
Answer» E.
26.

The project life cycle can be viewed of a mechanism, like

A. Control System
B. Execution System
C. Implementation System
D. Testing system
Answer» B. Execution System
27.

In matrix-organized projects, the PM controls

A. Functional decisions
B. Administrative decisions
C. Technological decisions
D. Technical decisions
Answer» C. Technological decisions
28.

The manner in which the process of risk management is conducted depends on

A. Management impact
B. Technological impact
C. Environment impact
D. Conflicts
Answer» D. Conflicts
29.

The fourth sub process in the risk management process is

A. Qualitative Risk Analysis
B. Quantitative Risk Analysis
C. Risk monitoring and controlling
D. Risk Response
Answer» C. Risk monitoring and controlling
30.

A wide-ranging method for addressing problems that considers multiple and interacting relationships is called

A. Analytic approach
B. Systematic approach
C. Break-down approach
D. Technological approach
Answer» C. Break-down approach
31.

Anything outside a system (the project) that can affect or be affected by the system, is known as

A. Environment
B. Medium
C. Channel
D. Boundary matrix
Answer» B. Medium
32.

Problematic cultural issues include the group's perception of time and the manner of

A. Staffing personnel
B. Staffing projects
C. linguistics
D. Collaboration
Answer» C. linguistics
33.

A ratio to evaluate a proposed course of action is known as

A. Low-cost
B. Benefit-cost
C. High-cost
D. Cost-ratio
Answer» C. High-cost
34.

From the initiation of the project to its termination, crises appear without

A. Solution
B. Pause
C. Limitations
D. Warning
Answer» E.
35.

Apart from the value of a fine design, the economic value of the time saved is immense. The value can be derived from

A. 1 source
B. 2 sources
C. 3 sources
D. 4 sources
Answer» C. 3 sources
36.

In matrix approach, there is less anxiety about what happens when the project is completed than is typical of

A. Pure Project Organization
B. Mixed Organizational System
C. Virtual Organization
D. Functional Form Organization
Answer» B. Mixed Organizational System
37.

The database must be available to everyone proposing to perform

A. Risk Response
B. Risk management
C. Risk analysis
D. Risk Identification
Answer» C. Risk analysis
38.

The phase that takes into account, the realities of the firm's limitations on facilities, capital and personnel is

A. Modelling phase
B. Planning phase
C. Analysis phase
D. Execution phase
Answer» B. Planning phase
39.

A solution in which both parties are better off in the outcome is known as

A. Pareto-Optimal Solution
B. win-lose solution
C. win-win solution
D. lose-lose solution
Answer» D. lose-lose solution
40.

The second set of trade-offs concerns sacrificing smoothness of running the project team for

A. Functional progress
B. Scheduling
C. Managerial progress
D. Technical progress
Answer» E.
41.

Getting many more projects than management expected, is a symptom of a misaligned

A. Strategy
B. Vision
C. Portfolio
D. Mission
Answer» D. Mission
42.

All members of the project work force are directly responsible to the

A. Marketing Manager
B. Functional Manager
C. Technical Manager
D. Project Manager
Answer» E.
43.

The need to consider the many environments of almost any project is clear while examining

A. Risk analysis
B. Risk management
C. Risk identification
D. Risk Response
Answer» C. Risk identification
44.

A primary disadvantage of functional elements is the part that is not the focus of activity, is

A. Manager
B. Technical team
C. Scope
D. Client
Answer» E.
45.

A monitoring technique, that is closely related to network diagrams, Is

A. Pi-Chart
B. Bar-Chart
C. Gantt Chart
D. Histogram
Answer» D. Histogram
46.

The hybridization of the mixed form leads to

A. Flexibility
B. Inflexibility
C. Complexity
D. Poor Quality
Answer» B. Inflexibility
47.

If project is organized as a weak matrix, the PM seeks a commitment of work from the

A. Personnels
B. Subcontractors
C. Senior Management
D. Functional Department
Answer» E.
48.

The PM must perceive sufficient technical knowledge to

A. Outsiders
B. Clients
C. Senior Executives
D. both b and c
Answer» E.
49.

The second credibility required by PM is known as

A. Functional Credibility
B. Technical Credibility
C. Administrative Credibility
D. Competence Credibility
Answer» D. Competence Credibility
50.

If project's organizational format is a strong matrix, the PM seeks a commitment of people from the

A. Functional Department
B. Technical Department
C. Senior Management
D. Personnels
Answer» B. Technical Department