1.

Which of these is an appraisal cost?

A. Inspection and testing of incoming material
B. New product review
C. Complaint adjustment
D. Rework
Answer» B. New product review
2.

Consider a mortgage refinance operation at a bank. If the average completion rate for submitted applications is 100 completions per day, and there are 1500 applications waiting for processing, the process cycle time is ___________

A. 15 hrs
B. 15 days
C. 150 days
D. 15.33 days
Answer» C. 150 days
3.

If the value-add time for a process is 10% of the process cycle time, what will be the PCE or Process Cycle efficiency of the mentioned process?

A. 10%
B. 12%
C. 23%
D. 14%
Answer» B. 12%
4.

Process performance is not predictable unless the process behavior is stable .

A. True
B. False
Answer» B. False
5.

For any stable process, if the process follows 6 sigma quality performance, how many products it will produce defective?

A. 1.9946 ppm
B. 3.4000 ppm
C. 1200 ppm
D. 934 ppm
Answer» C. 1200 ppm
6.

Using 3 sigma quality performances, we get 2700 products produced which are nonconforming. If we operate on the 3- performance, and we produce 100 independent product components, what is the probability of finding a product not defective?

A. 0.7891
B. 0.27
C. 0.7631
D. 0.007631
Answer» D. 0.007631
7.

In 3- quality performance, the probability of producing a conforming product is _______

A. 0.9973
B. 0.9500
C. 1
D. 0.9467
Answer» B. 0.9500
8.

PDSA is expanded as ____________

A. Plan-Define-Study-Analyze
B. Plan-Define-Study-Act
C. Plan-Do-Study-Act
D. Plan-Do-Study-Analyze
Answer» D. Plan-Do-Study-Analyze