| 1. |
The lateral leachate collection pipes shall slope towards ________ pipe. |
| A. | Sump |
| B. | Drain |
| C. | Main |
| D. | Longitude |
| Answer» D. Longitude | |
| 2. |
What is the formula for quantification of leachate generation from landfill? |
| A. | I = P P (CR/O) AET +/- S |
| B. | P = I P (CR/O) AET +/- S |
| C. | I = S P (CR/O) AET +/- P |
| D. | I = P S (CR/O) AET +/- Y |
| Answer» B. P = I P (CR/O) AET +/- S | |
| 3. |
Drainage pipes of leachate collection system is filled with ________ |
| A. | Gravel |
| B. | Dust |
| C. | Clay |
| D. | Grass |
| Answer» B. Dust | |
| 4. |
PVC liners are suitable for landfills. |
| A. | True |
| B. | False |
| Answer» B. False | |
| 5. |
Bentonite is mixed when there is not enough clay available at a site to construct a soil liner. |
| A. | True |
| B. | False |
| Answer» B. False | |
| 6. |
Excavation of soil in a location for liner is known as ________ pit. |
| A. | Dig |
| B. | Borrow |
| C. | Barrow |
| D. | Excavated |
| Answer» C. Barrow | |