1.

The Remodelling of canal system is done to __________

A. beautify the canal surroundings
B. correct deformations in the canal
C. exhibit the canal in exhibition
D. widen up the channel section
Answer» C. exhibit the canal in exhibition
2.

Berm is _____________

A. a horizontal strip at the N.S.L
B. a device to remove silt
C. another name of the canal bank
D. a gap created in the bank of the canal
Answer» B. a device to remove silt
3.

In Long reach system, only a portion of full supply discharge is taken in the compartment.

A. True
B. False
Answer» C.
4.

In the external silting method, subsidiary banks are constructed which run parallel to canal main banks.

A. True
B. False
Answer» B. False
5.

Which of the following statement is wrong about the internal silting method?

A. The extra strength is gained by increasing the section of the banks
B. The additional soil is derived from the natural process of silting internally
C. This method of strengthening the canal is very cheap, simple and efficient
D. To decelerate the silting process low submersible spurs may be constructed
Answer» E.
6.

Internal silting method and external silting method are the methods of ________________

A. strengthening of canal banks
B. formation of berms
C. silt removal
D. formation of breaches
Answer» B. formation of berms
7.

Which of the following is not a preventive measure for the maintenance of the canal?

A. Strengthening of canal banks
B. Formation of berms by internal silting
C. Provision of Pushta or cover to the saturation line
D. Silt removal
Answer» E.
8.

Which of the following is not a reason which leads to a canal breach?

A. Due to faulty design and construction of banks
B. Due to leakage or piping
C. Due to the maintenance of service roads
D. Due to intentional cuts made by cultivators
Answer» D. Due to intentional cuts made by cultivators
9.

The berms help in checking excessive loss of water due to seepage.

A. True
B. False
Answer» B. False