MCQOPTIONS
Saved Bookmarks
This section includes 6 Mcqs, each offering curated multiple-choice questions to sharpen your Irrigation Engineering knowledge and support exam preparation. Choose a topic below to get started.
1. |
Convert the hydropower potential of 84 GW at 60% load factor into Trillion watts hour. |
A. | 441 TWh |
B. | 735 TWh |
C. | 553 TWh |
D. | 345 TWh |
Answer» B. 735 TWh | |
2. |
Which one is the first nuclear power plant in India? |
A. | Tarapur atomic power station |
B. | Kaiga atomic power station |
C. | Rawatbhata Atomic power station |
D. | Narora atomic power station |
Answer» B. Kaiga atomic power station | |
3. |
In India, the nuclear power generation is about ____________ of the total power generation. |
A. | 3% |
B. | 4% |
C. | 5% |
D. | 6% |
Answer» B. 4% | |
4. |
What is the correct expansion of DAE? |
A. | The Department of Atomic Energy |
B. | The Discipline of Atomic Energy |
C. | The Division of Atomic Energy |
D. | The Domain of Atomic Energy |
Answer» B. The Discipline of Atomic Energy | |
5. |
The first power station of India was installed at _________________ |
A. | Mysore |
B. | Bombay |
C. | Darjeeling |
D. | Bangalore |
Answer» D. Bangalore | |
6. |
As per estimate made by the Central Electricity Authority, the potential of the country is accessed at 84 GW at load factor value of _________________ |
A. | 40% |
B. | 60% |
C. | 80% |
D. | 20% |
Answer» C. 80% | |