1. |
Estimate the quantities of brickwork and plastering required in a wall 4m long, 3m high and 30 cm thick. Calculate also the cost if the rate of brickwork is Rs.32.00 per cu.m and of plastering is Rs. 8.50 per sq.m. |
A. | Rs.1456.00 |
B. | Rs.1686.00 |
C. | Rs.1356.00 |
D. | Rs.1556.00 |
Answer» D. Rs.1556.00 | |
2. |
The expected out turn of 2.5 cm cement concrete floor per mason per day _____________ |
A. | 2.5 sqm |
B. | 5.0 sqm |
C. | 7.5 sqm |
D. | 10 sqm |
Answer» D. 10 sqm | |