1.

Estimate the quantities of brickwork and plastering required in a wall 4m long, 3m high and 30 cm thick. Calculate also the cost if the rate of brickwork is Rs.32.00 per cu.m and of plastering is Rs. 8.50 per sq.m.

A. Rs.1456.00
B. Rs.1686.00
C. Rs.1356.00
D. Rs.1556.00
Answer» D. Rs.1556.00
2.

The expected out turn of 2.5 cm cement concrete floor per mason per day _____________

A. 2.5 sqm
B. 5.0 sqm
C. 7.5 sqm
D. 10 sqm
Answer» D. 10 sqm