Explore topic-wise MCQs in Building Construction.

This section includes 10 Mcqs, each offering curated multiple-choice questions to sharpen your Building Construction knowledge and support exam preparation. Choose a topic below to get started.

1.

Effective length of a continuous wall is 0.8L when there is no opening within _________ of the height of the wall.

A. One-fourth
B. One-eighth
C. One-sixteenth
D. One-half
Answer» C. One-sixteenth
2.

Effective length of a continuous wall supported by piers is ___________

A. 0.8L
B. 1.0L
C. 1.5L
D. 2.0L
Answer» B. 1.0L
3.

The effective thickness of a __________ column is equal to the actual thickness.

A. Square
B. Rectangular
C. Circular
D. Trapezoidal
Answer» C. Circular
4.

The stiffening coefficient varies inversely with the __________

A. Actual thickness of the wall
B. Thickness of pier
C. Spacing of wall
D. Width of pier
Answer» B. Thickness of pier
5.

The effective thickness should be _________ of the sum of actual thicknesses of the two skins of a cavity wall if both the skins have uniform thickness throughout.

A. One-fourth
B. Half
C. Two-thirds
D. One-third
Answer» D. One-third
6.

Effective thickness of masonry is reduced if the eccentricity ratio exceeds ___________

A. 1/2
B. 1/3
C. 1/5
D. 1/6
Answer» E.
7.

Effective length of a wall when it is supported by a buttress only at one end is __________

A. 1.5L
B. 1.0L
C. 0.5L
D. 2.0L
Answer» B. 1.0L
8.

Effective thickness is equal to the actual thickness for solid walls.

A. True
B. False
Answer» B. False
9.

Effective length of a wall supported by a buttress at each end is ________

A. 0.8L
B. 1.0L
C. 1.5L
D. 2.0L
Answer» C. 1.5L
10.

L is the length measured between _________ of piers.

A. Ends
B. Centers
C. Edges
D. Faces
Answer» C. Edges