1.

A large work or project may consists of several building or small works and each of these work is known as ___________

A. sub-work
B. sub-project
C. sub-head
D. sub-construction
Answer» B. sub-project
2.

________________ is the amount provided in the estimate and bill of quantities for some specialised work to be done by a specialised firm; whose details are not known at the time of preparing estimate.

A. Prime cost
B. Provisional sum
C. Capital cost
D. Building cost index
Answer» C. Capital cost
3.

__________ is prepared on the basis of plinth area of building, the rate being deducted from the cost of similar building having similar specification, heights and construction, in the locality.

A. Cube Rate Estimate
B. Supplementary Estimate
C. Maintenance Estimate
D. Plinth Area Estimate
Answer» E.
4.

Approximate cost of sewerage project for a population of one lakh@ Rs. 10/- head works out as Rs. 10 lakh.

A. True
B. False
Answer» C.