1. |
Once a project is planned in terms of events and activities what next is important? |
A. | Schedule |
B. | Activity |
C. | Time |
D. | Finishing |
Answer» B. Activity | |
2. |
In developing a network diagram time flows from right to left. |
A. | True |
B. | False |
Answer» C. | |
3. |
The basic purpose of drawing a network diagram and its analysis is to control the activities strictly limited to time and sequence of events. |
A. | True |
B. | False |
Answer» B. False | |