1.

Once a project is planned in terms of events and activities what next is important?

A. Schedule
B. Activity
C. Time
D. Finishing
Answer» B. Activity
2.

In developing a network diagram time flows from right to left.

A. True
B. False
Answer» C.
3.

The basic purpose of drawing a network diagram and its analysis is to control the activities strictly limited to time and sequence of events.

A. True
B. False
Answer» B. False