Explore topic-wise MCQs in Construction & Building Materials.

This section includes 3 Mcqs, each offering curated multiple-choice questions to sharpen your Construction & Building Materials knowledge and support exam preparation. Choose a topic below to get started.

1.

The _______ can be effectively adopted for excavation in or at the foot of the slope of a hill.

A. Freezing process
B. Cement grouting
C. Pumping
D. Well Point System
Answer» B. Cement grouting
2.

The ________ can be adopted as an aid in construction to stop rock movements and to increase the permeability of the strata as in the case of oil wells.

A. Chemical grouting
B. Cement grouting
C. Pumping
D. Well Point System
Answer» B. Cement grouting
3.

In which method a refrigeration plant of required capacity is needed to be installed near the site of work?

A. Pumping
B. Well Point System
C. Freezing process
D. Electro osmosis process
Answer» D. Electro osmosis process