1. |
The type of canal alignment which involves maximum CD works is a ______________ |
A. | ridge canal |
B. | contour canal |
C. | side slope canal |
D. | both ridge and contour canal |
Answer» C. side slope canal | |
2. |
In order to reduce the CD works, the artificial canals are generally aligned along the ridgeline. |
A. | True |
B. | False |
Answer» B. False | |
3. |
Inlets and Outlets are inferior to aqueduct or super-passage type of work. |
A. | True |
B. | False |
Answer» B. False | |
4. |
The relative bed levels of the canal and the drainage may be changed and manipulated by _________________ |
A. | changing the alignment |
B. | changing the positions of the water table |
C. | altering the head level |
D. | use of dewatering equipment |
Answer» B. changing the positions of the water table | |
5. |
The canal alignment is finalized only after finalizing the CD works. |
A. | True |
B. | False |
Answer» B. False | |