Explore topic-wise MCQs in Concrete Technology.

This section includes 9 Mcqs, each offering curated multiple-choice questions to sharpen your Concrete Technology knowledge and support exam preparation. Choose a topic below to get started.

1.

At what temperature the heat is supplied to concrete to remove moisture in oC?

A. 35
B. 120-150
C. 100
D. 60-150
Answer» C. 100
2.

What is the time required to give heating to remove the moisture from the concrete?

A. 6-8 hrs
B. 10 hrs
C. 24 hrs
D. 48 hrs
Answer» B. 10 hrs
3.

Water-filled voids ranges from _______ % of the total volume of the component for gap-graded concrete.

A. 5
B. 15
C. 10
D. 20
Answer» C. 10
4.

Water-filled voids ranges from _______ % of the total volume of the component for dense concrete.

A. 5
B. 15
C. 10
D. 20
Answer» B. 15
5.

________ viscosity liquid monomers are impregnated with the hardened cement composite structure.

A. High
B. 0
C. Low
D. Very high
Answer» D. Very high
6.

What is the 7 day bending failure stress in N/mm2?

A. 40
B. 1500
C. 3.3
D. 180
Answer» D. 180
7.

What is the 10 day bending young s modulus in N/mm2?

A. 40
B. 1500
C. 3.4
D. 180
Answer» E.
8.

What is the 10 day compressive young s modulus in N/mm2?

A. 40
B. 1500
C. 3.4
D. 180
Answer» C. 3.4
9.

What is the 10 day compressive failure stress in N/mm2?

A. 40
B. 1500
C. 3.4
D. 180
Answer» B. 1500