MCQOPTIONS
Saved Bookmarks
This section includes 6 Mcqs, each offering curated multiple-choice questions to sharpen your Railway Engineering knowledge and support exam preparation. Choose a topic below to get started.
| 1. |
In the collection of ballast along the cess, what are the materials passing through 6mm square mesh called? |
| A. | Fine aggregates |
| B. | Dust |
| C. | Coarse aggregates |
| D. | Silicates |
| Answer» C. Coarse aggregates | |
| 2. |
Where is the stacking of ballast done? |
| A. | Alongside the railway line |
| B. | In containers |
| C. | In specially built sheds |
| D. | Stored in the trucks |
| Answer» B. In containers | |
| 3. |
How is the collection of Ballast done? |
| A. | From Ballast depots |
| B. | Collection along the cess |
| C. | From ballast depot or along the cess |
| D. | From mine sites |
| Answer» D. From mine sites | |
| 4. |
What is the shrinkage allowance when ballast is supplied by Wagons? |
| A. | 25% |
| B. | 50% |
| C. | 8% |
| D. | 32% |
| Answer» D. 32% | |
| 5. |
What should be the shape of Ballast stones? |
| A. | Cubical |
| B. | Rounded |
| C. | Sub-rounded |
| D. | Flaky |
| Answer» B. Rounded | |
| 6. |
What should be the maximum percentage of aggregates retained on the 65mm sieve? |
| A. | 10% |
| B. | 5% |
| C. | 16% |
| D. | 12% |
| Answer» C. 16% | |