MCQOPTIONS
Saved Bookmarks
This section includes 14 Mcqs, each offering curated multiple-choice questions to sharpen your Irrigation Engineering knowledge and support exam preparation. Choose a topic below to get started.
1. |
What is the approximate percentage of light reinforcement that is provided in the top of the reinforced concrete slabs at the base? |
A. | 0.50% of the concrete area |
B. | 0.45% of the concrete area |
C. | 0.30% of the concrete area |
D. | 0.25% of the concrete area |
Answer» E. | |
2. |
The minimum slope of the chute is governed by the condition that _____________ |
A. | the subcritical flow must be maintained |
B. | the supercritical flow must be maintained |
C. | a critical flow must be maintained |
D. | maybe supercritical or subcritical flow is possible |
Answer» C. a critical flow must be maintained | |
3. |
Calculate the freeboard for the top levels of the side walls if the mean velocity of water in the chute reach is 3.5 m/s and the mean depth of water in the chute reach under consideration is 4.7 m. |
A. | 0.60 m |
B. | 1 m |
C. | 0.85 m |
D. | 0.55 m |
Answer» D. 0.55 m | |
4. |
Which of the following curve is provided when the slope of the chute changes from milder to steeper? |
A. | Concave vertical curve |
B. | Hyperbolic curve |
C. | Convex vertical curve |
D. | Straight plan |
Answer» D. Straight plan | |
5. |
The type of spillway which is provided on narrow valleys where no side flanks are available is ____________________ |
A. | ogee spillway |
B. | chute spillway |
C. | side-channel spillway |
D. | straight drop spillway |
Answer» D. straight drop spillway | |
6. |
The portion of a chute spillway which is known as its control structure is ________________ |
A. | low ogee weir |
B. | chute channel |
C. | approach channel leading the water from the reservoir to the ogee weir |
D. | silting basin at its bottom |
Answer» B. chute channel | |
7. |
The spillway which may sometimes be called as a waste weir is ______________________ |
A. | an ogee spillway |
B. | a trough spillway |
C. | a shaft spillway |
D. | a siphon spillway |
Answer» C. a shaft spillway | |
8. |
The side slope of approach channel of chute spillway is ___________________ |
A. | 1:1 |
B. | 1:1 ( frac{1}{2} ) |
C. | 1:3 |
D. | 1:2.5 |
Answer» B. 1:1 ( frac{1}{2} ) | |
9. |
Whenever the slope of chute changes from steeper to milder ____________________ curve shall be provided. |
A. | a concave vertical curve |
B. | a convex vertical curve |
C. | a hyperbolic curve |
D. | a parabolic curve |
Answer» B. a convex vertical curve | |
10. |
The surplus reservoir water after spilling over the crest of the spillway flows on the chute is __________________ |
A. | parallel to the crest in a trough spillway |
B. | parallel to the crest in a side-channel spillway |
C. | perpendicular to the crest in a side-channel spillway |
D. | obliquely to the crest in a chute spillway |
Answer» C. perpendicular to the crest in a side-channel spillway | |
11. |
The famous Bhakra dam of India is provided with ________________ |
A. | trough spillway |
B. | ogee spillway |
C. | shaft spillway |
D. | siphon spillway |
Answer» B. ogee spillway | |
12. |
The spillway which can be adopted with ease on gravity as well as earthen dams is _________________ |
A. | ogee spillway |
B. | chute spillway |
C. | both ogee and chute spillway |
D. | straight drop spillway |
Answer» C. both ogee and chute spillway | |
13. |
If the spillway is constructed in continuation to the dam at one end, it may be called as ________ |
A. | saddle weir |
B. | flank weir |
C. | waste weir |
D. | temporary weir |
Answer» C. waste weir | |
14. |
Which of the following is the simplest type of spillway which can be provided independently and at low costs? |
A. | Ogee spillway |
B. | Trough spillway |
C. | Siphon spillway |
D. | Saddle spillway |
Answer» C. Siphon spillway | |