Explore topic-wise MCQs in Engineering Metrology.

This section includes 11 Mcqs, each offering curated multiple-choice questions to sharpen your Engineering Metrology knowledge and support exam preparation. Choose a topic below to get started.

1.

Which of the following option is true for given statements about automatic inspection machines?Statement 1: Safety devices are incorporated to avoid damage to the gauging fixture.Statement 2: Gauging devices entering the part is positively pushed.

A. T, T
B. T, F
C. F, T
D. F, F
Answer» C. F, T
2.

Which of the following statement is true for automatic inspection machines?Statement 1: Measurement information is displayed on the screen.Statement 2: Bad parts are not segregated automatically.

A. T, F
B. F, F
C. F, T
D. T, T
Answer» B. F, F
3.

WHICH_OF_THE_FOLLOWING_OPTION_IS_TRUE_FOR_GIVEN_STATEMENTS_ABOUT_AUTOMATIC_INSPECTION_MACHINES??$

A.
B.
Answer» C.
4.

Which of the following is true about the design of structure of automatic inspection machine?

A. Separate structure is designed for transportation and gauging system
B. Same structure is designed for transportation and gauging system
C. Anti vibration mounts are placed only one leg of gauging structure
D. Anti vibration mounts are placed only on two front legs of gauging structure
Answer» B. Same structure is designed for transportation and gauging system
5.

Why retooling is fast and less expensive in automatic inspection machines?

A. Only hardware changes are needed
B. Both hardware and software changes are needed
C. No hardware changes are needed
D. Software program doesn’t need any change
Answer» D. Software program doesn‚Äö√Ñ√∂‚àö√ë‚àö¬•t need any change
6.

Which of the following statement is true for automatic inspection machines?

A.
B.
Answer» B.
7.

Which of the following is true about probes used in automatic inspection machines?

A. Retractable type
B. Non-retractable type
C. Auxiliary probe is not used
D. Heads of probes are not held back till the part is in gauging position
Answer» B. Non-retractable type
8.

What is done to avoid out-of-sequence mishaps in automatic inspection machine?

A. Clamping between centres and sequence of part lifting are linked on different controls
B. Clamping between centres and gauge fixtures are linked on different controls
C. Sequence of part lifting and gauge fixtures are linked on different controls
D. Sequence of part lifting, clamping between centres and gauge fixtures are linked on same controls
Answer» E.
9.

Which of the following is true about the self-diagnostic system present in automatic inspection machines?

A. Increase downtime
B. Easy but slow identification
C. Improved efficiency of maintenance
D. Increase settling time
Answer» D. Increase settling time
10.

What is not a use of rocker-arm components in automatic gauging system?

A. Amplify motion
B. Enable probe to reach very difficult areas
C. Enable positioning of part
D. Transfer movement from datum through not more than one pivot points
Answer» E.
11.

Which of the following is not true about automatic inspection machine?

A. Human intervention is required to judge the quality
B. Consists a logic system
C. Self diagnostic system is present
D. Microprocessors are present
Answer» B. Consists a logic system