1. |
Quality management system improves perception of customers towards company. |
A. | True |
B. | False |
Answer» B. False | |
2. |
The basic requirement for the success of any quality control plan is the availability of experienced, knowledgeable and trained personnel at all levels. |
A. | True |
B. | False |
Answer» B. False | |
3. |
For walls, columns and vertical faces of all structural members, the form work is generally removed after __________ |
A. | 24 to 48 hours |
B. | 3 days |
C. | 7 days |
D. | 14 days |